60 years focused on metallurgy / mine / water industry pump system

E-mail|Contact US|Chinese|English|Russian

TEL:86-21-59167911
Email:frank@sanlianpump.com

Turkey project

Date:2017-07-05  Views:863

Project description: referring to the contract signed by Turkey ICDAS (hereinafter referred to as "the owner") and China machinery import and export corporation (CMEC) on 26 February 2008, contract no. : IC/cm-2008 / A

Project:Turkey BEKIRLI 2 x 600MW supercritical coal-fired power station unit 1 is equipped with 4 open circulating cooling water booster pumps.

Equipment name: open cycle cooling water booster pump.

Installation site and elevation of the equipment: 0.00m in the motor room.

Power plant type: 2 * 600MW supercritical condensing steam turbine generator set.

Unit capacity and operation mode

The capacity of turbo generating set is 2 * 600 MW.

The operating mode of the unit is to adopt the basic load and participate in the mode operation.

The configuration and operation mode of the booster pump

The cold oil side of each unit is equipped with two open circulating cooling water booster pumps, one by one. The closed cycle heat exchanger side is equipped with two open circulating cooling water booster pumps, one by one. A total of 4 booster pumps are installed in 1 unit of this project.

Delivery medium: seawater

Vertical hsv300-250-400A, flow rate: 907.5 m3 / h, lift: 34.5 m, motor model Y3, 315L1-4/160kw. Shell, impeller material 316L

Heat exchanger side boost pump horizontal hs600-500-650b, flow: 3125 m3 / h, yangcheng: 34.5 m motor model yk450-6/450kw. Shell, impeller material 316L